21 Houses under construction ranging between 70% to 90% completion rate with exception of 1 house at 53%
Colour Scheme of the interior & exterior paints, tiles and sinks selected by the Mustique Charitable Trust office to reflect the standard of Mustique Charitable Trusts
Trustee makes two (2) visits to the site and pleased with the project progress and quality of works
Project Committee held its 4th meeting on site and are pleased with the progress as the 1st phase of 21 houses is nearing the completion stage.